Twenty scenario-based questions aligned to the current Examination Content Outline and the PMBOK® Guide Eighth Edition. Every answer explains why the correct option is correct — and why the tempting one is not.
PMI updated the PMP exam on 9 July 2026, aligning it to the PMBOK® Guide Eighth Edition. The most important change for anyone studying is the shift in domain weightings.
| Domain | Current weighting | Previous |
|---|---|---|
| People | 33% | 42% |
| Process | 41% | 50% |
| Business Environment | 26% | 8% |
Business Environment more than tripled. If you are studying from material that still shows 42 / 50 / 8, it predates the current exam — and the questions underneath it almost certainly have not been rewritten either. That single check will tell you whether a free question bank is worth your time.
Around 60% of the exam now reflects agile and hybrid ways of working, woven through all three domains rather than sitting in a section of its own.
Not because they did not know the material. Because they were taught content when they needed to be taught judgement.
The exam gives you a situation and four plausible answers. Three of them are things a reasonable project manager might actually do. Knowing the definition of a work breakdown structure will not tell you which one to pick.
That is why every question below is situational, and why each answer explains the trap as well as the solution. Recognising why a wrong answer is attractive is the skill the exam measures.
These twenty questions are drawn from the practice bank used on the NLC Project Power PMP® preparation programme, which runs to 120 questions across twelve lessons.
I am Norma Lynch, a PMI Authorised Training Partner instructor based in Midleton, County Cork. I am a part-time senior lecturer at the Institute of Project Management and a former board member of the PMI Ireland Chapter. I have spent my career teaching project managers to think like project managers — and, for the exam, to think like the people who write the questions.
You need either a four-year degree and 36 months leading projects, or a secondary diploma and 60 months, plus 35 contact hours of formal project management education. Experience must be recent — check the current window on pmi.org before applying.
Most people need six to eight weeks at around five hours a week, assuming they already have the project experience behind them.
It helps, and PMI members download it free. But reading it cover to cover is not what passes the exam. Working situational questions is.
Yes. They were written from the current Examination Content Outline and the PMBOK® Guide Eighth Edition, not updated from an older set.